Licensed removal of an external AIB canopy at a live self-storage site on Bellotts Road, managed around public access and neighbouring units. Fully enclosed, air-monitored and handed back with a complete waste and clearance record.
Every stage ran under the Control of Asbestos Regulations 2012: notification to the HSE, a sealed and smoke-tested enclosure, negative pressure with monitored airflow, and a four-stage clearance by an independent analyst before handback.
Innov8 UK Group carries out licensed asbestos removal and asbestos removal in Bath and across the UK, with depots in Manchester, Carlisle and London. Every project — from a single garage to live rail and industrial sites — gets the same controls, the same paperwork and the same honest advice.
Following a recent inquiry from the client, IUG was requested to conduct a site visit to evaluate the recommended remedial actions outlined in the asbestos survey completed by P J Foley on the agreed date. The upcoming remedial works necessitate the removal of the licensed asbestos materials identified above the entrance door, leading to the staircase, to enable the project’s progression. The building was vacant at the time of the removal works, apart from IUG operatives carrying various non-licensed removal works.
IUG commenced the licensed asbestos removal works on the agreed date and completed the project on programme.
completed over a duration of 2 days. The scope of work involves the removal of Asbestos Insulating Board (AIB) canopy (soffit board) comprising of one sheet measuring 2m x 1m This sheet is secured to timber battens using 12 nails.
All asbestos removal works were conducted under fully controlled conditions within a purpose-built enclosure maintained under negative pressure. To minimise fibre release, wetting techniques and shadow vacuuming was employed throughout the process. The work was carried out in a systematic and methodical manner.
OBSTRUCTIONS MAKING ACCESS AND THE WORKS MORE DIFFICULT