Combined licensed AIB and non-licensed removal across multiple floors, with enclosures sequenced so strip-out followed straight behind. All waste consignment-noted and the job closed out with four-stage clearance certification.
A smoke-tested enclosure with airlock and baglock systems kept the work area fully contained, negative pressure units ran around the clock, and an independent analyst issued four-stage clearance before the enclosure came down.
If you need licensed asbestos removal or asbestos removal in Doncaster, Innov8 UK Group covers the whole of the UK from bases in Manchester, Carlisle and London — surveyed properly, quoted fixed and documented fully.
During works to Doncaster SPO Enclosure 1, additional Asbestos Insulating Board (AIB) panels were identified beyond the confirmed sow into the next building. Further investigation confirmed that the AIB ceiling panels continued into the adjoining Jarvis Building, which had been scheduled for works at a later stage. The continuation was taken flush with the brickwork, encapsulated and voided to define the boundary for the upcoming Phase 2 works.
A site visit carried out on the agreed date to the Jarvis Building confirmed further AIB ceiling panels to five separate areas within the front section of the building. These were noted for inclusion within the next phase of the licensed works.
A follow-up site meeting was held on the agreed date with the client the principal contractor’s representative, during which the programme of works and logistics were confirmed for commencement on Monday the agreed date. Prior to live asbestos removal, pre-works guano removal was required, along with the continuation of thermoplastic floor tiles and bitumen adhesive removal, as identified during Phase 1. These preparatory works were undertaken by a separate team ahead of the licensed removal activities to ensure safe access and egress to all designated work areas.
Guano was removed under controlled conditions pre licensed works for safe access and egress into the building. Enclosures & Air Management, Full enclosures with negative pressure units (NPUs) were erected where required, airlocks and bag locks were used to prevent fibre release, Smoke testing of enclosures prior to works.
OBSTRUCTIONS MAKING ACCESS AND THE WORKS MORE DIFFICULT A large quantity of guano was present to the building floor and surfaces; this was removed pre licensed works under controlled conditions.
Yes continuation, NW Report carried out by ACE the agreed date
No asbestos materials within this scope of works to be left in situ.